Microchip contacted HPE to rebuild the sumps on their cooling towers. They needed the first two towers completed by the first of June. HPE just finished the first cooling tower which has four sumps each.
Microchip’s facility group filled the tower to test for leakage and everything was leak free! Micro Chip was very happy with our approach and the quality of HPE’s work. They stated they are working on arranging the funding for the other two towers and HPE will be seeing a contract for this portion as well.
Ernie Fiorini was Special project manager and his crew Cody Port, Quade Doty, Jason Leblanc & Jared Abila. They completed this project in two weeks, which was a week ahead of schedule.
See the before and after pictures of our project at MicroChip.